🚗 EV Charging Time · NEC Article 625 · IEC 61851 Wallbox Sizing

100 kWh EV Battery Charging Time on 350 kW (IONITY / Electrify America 800V)

Real-world charging duration (10–80%, 20–80%, and 0–100%), range added per hour, charging cost, and electrical circuit breaker sizing.

10% to 80% Charge Time14 min20%–80%: 12 min
Full 0% to 100% Time24 minGrid Energy: 108.7 kWh
Driving Range Added / Hour+1838.6 km/h+1142.5 miles / hour
Circuit Breaker Required700A (NEC)505.2A @ 400V (3P)

Charging Time & Electrical Specification Table (100 kWh @ 350 kW)

EV Battery Usable Capacity100 kWh
Charger Output Rating350 kW (IONITY / Electrify America 800V)
10% to 80% Charging Time (Daily / Highway Optimal)14 min (0.24 hours)
20% to 80% Charging Time12 min (0.2 hours)
0% to 100% Full Charge Time (with BMS Tapering)24 min (0.41 hours)
Estimated Full Charge Cost (US / Germany / Sweden)$19.02 (US) · €36.96 (DE) · 179.35 kr (SE)
Continuous Current Draw & Breaker505.2 A @ 400V (3-Phase) → 700A NEC / 600A IEC Breaker

Frequently Asked Questions

How long does it take to charge a 100 kWh EV battery at 350 kW?

Charging a 100 kWh electric vehicle battery from 10% to 80% on a 350 kW (IONITY / Electrify America 800V) takes approximately 14 min (or 24 min for a full 0% to 100% charge including charger efficiency and BMS tapering).

What breaker size is required for a 350 kW EV charger?

At 400V (3-Phase), a 350 kW charger draws 505.2A continuously, requiring a 700A breaker under US NEC 625.41 (125% continuous load rule) or a 600A breaker under European IEC/NEK standards.